Palo Parado Bridge Project
August 2012
August 17, 2012
Results from Friday's storm event.

August 2, 2012
Project site looking east from Palo Parado Bridge (over I-19).

August 2, 2012
Soil Cement Batch Plant looking west.

August 2, 2012
Project site looking east from West Abutment.

August 2, 2012
Re-Bar Cage installed in drill shaft.

August 2, 2012
Concrete poured shaft and column transition.

August 2, 2012
Concrete poured shaft and column transition.

August 2, 2012
Crane for placing re-bar cage in shaft.

August 2, 2012
East Abutment Soil Cement Excavation.